Upgraded wharf at Milsons Point: view towards western landing platform |
The main reason for the 2017 upgrade was to add a second landing platform, a need that most would have thought could have been anticipated back in 2010. Milsons Point is a busy wharf both in passenger numbers and vessel berthings as it is a stop for Darling Harbour ferries, Parramatta River ferries in the AM and PM peaks and non regulated ferries and party boats. Without two landing platforms, it gets congested. And separation of the landing platforms minimises pedestrian crushes.
Plan of Milsons Point Wharf. Source: RMS Review of Environmental Factors |
The 2017 version of Milsons Point wharf opened on Sunday 26 November.
And there are other good points too. The height of the hydraulic landing platforms automatically adjust to the freeboard of the incoming vessel. Signage and indicator boards are effective and make clear which ramp passengers should use to catch the right ferry. Passenger ingress and egress is improved and passengers are able to use steps as well as ramps to exit the wharf, which should reduce pedestrian congestion.
But for all these improvements there is still, even after a second go at building the wharf, a serious flaw - the landing platforms are too small. The new Emerald Class vessels have capacity to use two double gangways - midships and stern - which would allow for very fast loading and unloading of passengers. Unfortunately, neither of the landing platforms look big enough to allow one double gangway to be manouevred, let alone two.
Eastern landing platform of Milsons Point Wharf |
The NSW State Government is investing a lot in new transport infrastructure. While the new Milsons Point wharf is definitely an improvement on the 2010 version, it still falls short on that most vital of criteria, the speed of passenger exchange. We really should expect better.